County board approves $53M Microsoft utility deal, minutes show

Microsoft pays for road, water and sewer work near its data center site, and five residents objected in public comment after the Oct. 6 vote.

By South Bend Paper AI Desk · November 7, 2026 at 9:02 PM

Updated November 11, 2026 at 9:30 AM: Updated Nov. 11 with what each construction bid package builds and more on the regional sewer capacity question, from the Oct. 6 minutes.

St. Joseph County's Redevelopment Commission voted 3-0 on Oct. 6 to approve a second agreement under which Microsoft pays for water, sewer and road work around its data center site in the northeast part of the county, newly posted minutes show. The agreement is worth $53,023,257.70.

Together with a first agreement approved in March, worth $12,577,375, that puts the total at "just over $65 million," Bill Schalliol, the county's executive director of economic development, told the commission. "All of these costs are being paid by Microsoft," he said. The money goes into an escrow account that the county draws on to pay contractors.

The minutes are in the packet for the commission's next regular meeting, at 9 a.m. Tuesday, Nov. 10, in the Council Chambers on the fourth floor of the County-City Building, 227 W. Jefferson Blvd., and on Zoom.

What the Microsoft money pays for

Schalliol broke the two agreements down as about $11.3 million for professional services, $12.2 million for buying land and right of way, about $39 million for construction, about $700,000 for other costs including extra sheriff's traffic enforcement, and $2 million for road repairs during construction. He said a third agreement is coming, likely $8.5 million to $9 million for work on Cleveland Road and perhaps Current and Bittersweet roads.

The construction is split into five projects, Schalliol told the commission:

  • Bid package A: water and sewer lines along Cleveland Road, including a section of gravity sewer. He said it would ideally go out to bid later in October.
  • Bid package B: a water line along Bittersweet Road from Day Road north to Cleveland Road and the site. Bids were opened in August, and the 60-day window to accept or reject them was ending that Friday, which he gave as the reason for the special meeting. Without approval that day, he said, the county would have to rebid it, pushing the award into November or December.
  • Bid package C: a water line and sewer along Douglas Road, from Veterans Parkway east to the new lift station. It completes a loop in the water network and brings sewer service to the site.
  • Bid package S: a sewer along Bittersweet Road from the bid package A work down to the new lift station.
  • Lift station: at the northwest corner of Bittersweet and Douglas roads, pumping sewage through a force main to Veterans Parkway.

The commission also voted 3-0 that day to expand three engineering contracts that Schalliol said Microsoft is paying for: DLZ Indiana's grew by $3,644,000 to $7,219,000, Lawson-Fisher Associates' by $1,645,000 to $2,295,000, and Lochmueller Group's by $175,000 to $505,400.

The regional sewer question

Schalliol called this the "immediate need" project: it serves the Microsoft site but is built to start a larger regional network. Extending bid package B to Day Road connects it to water lines serving the north Osceola area, he said, and the lines could later be extended north into Granger.

For now, the sewer would flow west into Mishawaka's network. As sewer capacity builds out along Veterans Parkway and the west Capital Avenue area, he said, "there's going to be a capacity limitation in the sewer network." The fix, he said, is a sewer line along Capital Avenue into pipes and a lift station site at Capital Avenue and Jefferson Road that were put in almost 25 years ago, when Jefferson was widened, but never used.

Schalliol said the agreement gives the county six months to set up a TIF district, or tax increment financing, which sets aside the growth in property taxes in an area for projects there, to help pay for that regional sewer. If that doesn't happen, he said, the parties will work out how to pay for it. "The TIF is not part and parcel to this agreement today," he said. He said the county had backed off its TIF proposal for now after hearing concerns, and that the regional sewer had been discussed in at least three earlier county-Mishawaka agreements.

Asked by commission member Dennis Jordan about Mishawaka going ahead on its own, Schalliol said Mishawaka has been "a good partner" but has an interest in annexation if the county cannot perform. The agreement, like the first one, provides for annexing parts of the site that are not taxable or not developed, he said.

He also described a provision letting Microsoft review public records requests for trade secrets before documents are released, with the county making the final decision, and letting the county bill the company up to $75,000 for the cost of handling requests.

Public comment came after the vote

Public comment is held at the end of the commission's meetings. Five people spoke after the Oct. 6 vote, according to the minutes.

Jan Cervelli, who lives on Woodington Court in Granger, objected to a special meeting "with very little public notice" and said the regional sewer plans "need to be explained to the public before this is moved forward."

Dan Caruso of New Carlisle said it "is silly to give the project ... the ability to determine what is a trade secret."

Ryan Callahan, who lives on Woodbourne Court in Granger, asked whether it "would have killed the deal" to state that a data center's power levels are not a trade secret, and said, "It's so bizarre to have public comment after the vote."

Steve Francis, who lives on Juday Lake Drive in Clay Township and described himself as an affected property owner downstream of the site, called the trade secret provision "an NDA in disguise" and said the commission was acting as "a rubber stamp." He also asked why Microsoft is paying for water and sewer lines "designed for other occupants of the whole Economic Development area." A fifth speaker, whose name is not clearly legible in the scanned minutes, called the decision "rushed."

Commission member Nick Troiola had urged county leaders and Microsoft to keep holding public forums. Schalliol said another open house was planned but not yet scheduled.

What's on Tuesday's agenda

The commission will be asked to approve a $675,000 contract with Christopher B. Burke Engineering to manage the county's work for the General Motors and Samsung SDI battery plant and the Amazon Web Services data center campuses in the Indiana Enterprise Center near New Carlisle through 2027. Burke has held the job since July 2023. With 2027, the yearly contracts add up to $3.2 million. The firm has been paid $2,306,889.64 so far, which the staff memo splits as $1,213,371.25 for the Amazon projects and $1,093,518.39 for the battery plant. The memo does not say who ultimately bears the cost.

Burke Engineering's yearly county contractsProject management for the battery plant and Amazon data centers, nominal dollars; 2027 is proposed
$0$200K$400K$600K$800K$1M$275K2023$650K2024$925K2025$675K2026$675K2027

Source: St. Joseph County Redevelopment Commission packet, Nov. 10, 2026

Also on the agenda:

  • Amazon lay-down yard returned. Ryan Companies, which builds for Amazon, ended its lease of county-owned land at Early and Walnut roads used for parking and staging during construction of the western data center buildings. The company says it planted about 6,000 saplings and 10 acres of prairie grass to restore the site, and that a $10,000 check was coming for June through October rent that stopped "due to an accounting error."
  • New Carlisle site. A proposed extension, to May 31, 2027, of the study period for EGDB Development LLC, which wants to build apartments on the county's former trailer park site at 494 and 496 E. Michigan St. in New Carlisle. The purchase price is to be set by appraisal.
  • More road design. A $141,260 addition to DLZ Indiana's landscape design contract for signs and masonry at three planned roundabouts in the Indiana Enterprise Center, raising it to $321,000.
  • Regional partnership. $14,000 a year for four years, $56,000 in all, from the commission's general fund for the South Bend-Elkhart Regional Partnership.
What did you think of this story?

More stories about Bill SchalliolMicrosoftSt. Joseph County Redevelopment Commission

Comments

No comments yet.

This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.