Microsoft seeks 30-foot sound wall at Cleveland Road data center site
The county zoning appeals board approved the wall 4-2 on Nov. 12, draft findings show, after staff said new industrial noise rules would not cover homes north of the Toll Road.

Updated November 28, 2026 at 6:48 AM: Updated Nov. 28: Draft findings posted for the board's Dec. 9 meeting show it approved the sound wall 4-2 on Nov. 12.
Microsoft Corp. asked St. Joseph County for permission to build a 30-foot-tall sound wall along the Indiana Toll Road at its data center site on Cleveland Road in Harris Township, according to the agenda packet for the county's Area Board of Zoning Appeals.
The vote
The board approved the variance on Nov. 12 by a 4-2 vote, according to draft findings of fact in the packet for its Dec. 9 meeting, where the board is set to adopt them. Tom Byers, Julie Lauck, Joe Velleman and Lance Roush voted yes. Chairman DJ Tavernier and Donny Ritsema voted no, and Sidney Shafer was absent. The findings say the wall could reduce noise reaching homes to the north from "the fully built out industrial property," and that strict application of the rules would keep the developer from voluntarily taking an extra step to keep data center sound and vibration from reaching neighborhoods. The board's Nov. 12 minutes have not yet been posted.
What was proposed
The request covers 12501 Cleveland Road plus an unaddressed parcel of about 158 acres to the west and one of about 17 acres to the east, all zoned industrial. County rules do not allow a structure that tall in the 50-foot minimum front yard next to a limited-access highway, so Microsoft needed a variance.
The county staff report, prepared by Area Plan Executive Director Shawn Klein, recommended approval. It says Microsoft proposed the wall "based on expressed public demand stemming from concerns related to noise generated by the approved data center use on this site and its potential impact on the use and value of residential properties north of the toll road."
The report notes that the county's zoning ordinance "does not contemplate the use of sound walls," which it says must sit in the front yard and be taller than the fences, landscape walls and berms now allowed there to contain noise from the site.
A gap in the new noise rules
The staff report also points to a limit in the county's industrial noise rules. Because the Toll Road right-of-way is wider than 150 feet, the report says, "the recently amended noise ordinance for industrial users would not be applicable to any noise or vibration generated at this site which may reach residential properties to the north at undesirable levels."
Without the wall, the report says, "strict application would deny homeowners in the area the enhanced protection from industrial noise which other residents of the County now enjoy." It adds that "adverse impacts from potential noise and vibration are a particularly common public concern currently for data center uses."
The Board of Commissioners approved the industrial noise ordinance passed by the County Council by a 3-0 vote on May 6, 2026, according to the board's minutes. County Council President Brian Tanner told commissioners that the ordinance protects existing businesses through grandfathering while setting limits for new development. Commissioner Carl Baxmeyer voted yes but said he still felt "there are considerable holes in this ordinance that need to be addressed" and was concerned about the cost of enforcement.
What the staff found
The report says the homes north of the site sit more than 300 feet away, on the other side of the I-80/90 right-of-way, and that mature trees line much of the highway's north side, so the wall would be hard to see from those homes. It says the wall would mostly be seen by Toll Road drivers passing at highway speed. The variance is void unless a building permit is approved within six months, and the wall has to match the site plan Microsoft submitted.
How the site got here
The County Council voted 6-3 on May 14, 2024, to rezone about 907 acres on both sides of Cleveland Road, south of the Toll Road and west of Bittersweet Road, from agricultural to industrial, subject to written commitments from the Area Plan Commission. The petitioner was St. Joe Farm LLC, and the land included 12501 Cleveland Road, according to council minutes. Council members Figg, Drake and Root voted no. The Nov. 12 packet lists Microsoft as the owner.
The packet does not say what the wall would cost, what it would be made of, or how much noise the data center is expected to make. Those details may be in Microsoft's application, which the packet doesn't fully include.
Also on the agenda
The board also had four smaller requests on Nov. 12: a garage setback in Clay Township, which draft findings show was approved; a lot split on Layton Road in Penn Township, also approved; and a narrow-lot request on Adams Road and a 70-foot billboard sought by Ritschard Bros., both of which are back on the board's Dec. 9 agenda.
More stories about MicrosoftSt. Joseph County Area Board of Zoning Appeals
- St. Joseph County Area Board of Zoning Appeals agenda and packet, Nov. 12, 2026(opens in a new tab)
- St. Joseph County Board of Commissioners minutes, May 6, 2026(opens in a new tab)
- St. Joseph County Council public hearing minutes, May 14, 2024(opens in a new tab)
- St. Joseph County Area Board of Zoning Appeals agenda and packet, Dec. 9, 2026 (draft Nov. 12 findings of fact)(opens in a new tab)
This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.
Comments
No comments yet.
Comments use your real name. To keep out fake accounts, we verify a US mobile number by text. We never show or share your number. Comment guidelines
Commenting as .
Replying to a comment.
Be civil and stay on topic. Criticism of anyone, including this paper, is welcome. Comments are reviewed before they appear. Guidelines
Comments open soon.