How South Bend changes a construction contract after the bid

State law caps added work at 20% of the original price, and the Wall Street rebuild shows how two change orders raised, then trimmed, a $2.6 million contract.

By South Bend Paper AI Desk · November 5, 2026 at 7:43 AM

When South Bend hires a contractor to rebuild a street or fix a sewer, the price it agrees to on bid day is rarely the price it pays at the end. The difference is handled through a document called a change order. Here is what that is, who approves it and what limits apply.

What a change order is

A change order is a written amendment to a public construction contract. It can add work, remove work or change the deadline. Under Indiana law, IC 36-1-12-18, once a change order is signed by the public board and the contractor, it "becomes an addendum to the contract."

In South Bend, the board that signs is the Board of Public Works, the same five-member board that opens bids and awards contracts. City engineers bring each change order to the board at a regular meeting, along with a one-page form showing the original contract amount, the change, the new total, the percent change and any added days.

The rules

State law sets several limits, according to the statute:

  • No change orders before work starts, except in an emergency. The board must declare the emergency and record what it was in its minutes.
  • A 20% cap on added scope. Change orders that expand the project can't add up to more than 20% of the original contract. Changes caused by conditions that couldn't reasonably have been foreseen don't count toward that cap.
  • Same project only. Every change must relate directly to the original job.
  • Same prices. If the change just adds more of something already in the contract, it's paid at the original unit price.
  • If a licensed engineer or architect is assigned to the project, that professional prepares the change order.

A final change order often trues up the contract to what was actually built. Because many road and sewer contracts are priced by the unit, by the square yard of sidewalk or cubic yard of dirt, the last change order can lower the price as well as raise it.

A local example: Wall Street

On May 27, 2025, the Board of Public Works awarded the Wall Street and Greenlawn Avenue improvements to Selge Construction Co. of Niles, Mich., for $2,592,256.25, according to the board's minutes. City records describe the work as "Improve storm sewer, add parking, pave," paid from the River East TIF district.

Change Order No. 1, approved Feb. 10, 2026, added $94,676.90, or 3.65%, and pushed the deadline from Oct. 3, 2025, to April 30, 2026. The line items attached to it include:

  • $43,882.80 to truck away 3,783 cubic yards of excess dirt
  • $17,415 for 129 square yards of colored sidewalk
  • $10,775.10 for clay excavation
  • $8,188 for changeable message boards
  • $8,020 for two lead service line replacements
  • $1,096 for four wayfinding signs to Potawatomi Zoo

The 209 extra days, Assistant City Engineer Leslie Biek told the board, were "due to weather-related delays for landscaping and tree planting scheduled for the spring," according to the minutes.

Change Order No. 2, the final one, approved July 28, 2026, cut $42,498.72. The final contract came to $2,644,434.44, about 2% over the original award, well under the 20% limit. The board approved a project completion affidavit for the same amount, which formally closes the contract.

When the emergency rule applies

The board has used the emergency exception, too. In October 2020, the city's original pick for alley paving in the Notre Dame Triangle area did not take the contract. With funding tied to 2020 and cold weather coming, engineers asked the board for an emergency change order under the state law, giving the next-lowest bidder, Walsh & Kelly, 14 days to finish. The board approved it Oct. 27, 2020, with a completion date of Nov. 14, records show.

Where to find them

Change orders and completion affidavits are posted with Board of Public Works documents in the city's online records archive, and appear on the board's agendas, which list each change's amount and percent.

What did you think of this story?

More stories about Selge ConstructionSouth Bend Board of Public WorksWall Street and Greenlawn Avenue Improvements

Comments

No comments yet.

This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.