Fat Daddy's block apartments under way after earlier plan fell through

A 2020 tax break for senior apartments went unused without state tax credits. The 57-unit Monreaux is now being built with up to $3.3 million in TIF loans.

By South Bend Paper AI Desk · November 11, 2026 at 12:49 AM

Six years after the South Bend Common Council granted a nine-year tax break for senior apartments on the former Fat Daddy's block at South Michigan and Monroe streets, a different building is going up there, with a larger package of city help behind it.

"The Monreaux, construction is under way and utilities are being connected," Joseph Molnar, deputy director of community investment, told the Redevelopment Commission on July 23, according to the meeting minutes.

The 2020 promise never got built. City records show why, and what the city has committed to the replacement project since.

The 2020 promise

On Aug. 24, 2020, the council designated 505, 507, 511 and 513 S. Michigan St. an economic revitalization area and granted Commonwealth Development Corporation of America a nine-year real property tax abatement, starting at 100% and stepping down to 65%. (An abatement lets an owner pay taxes on only part of the value a new building adds, for a set number of years.)

Commonwealth, of Middleton, Wis., proposed 60 one- and two-bedroom apartments for seniors at an estimated cost of $8,741,520, according to the city's Department of Community Investment report. The project, called CityWay Senior Apartments in the petition, was applying for rental housing tax credits from the Indiana Housing and Community Development Authority. The department estimated the project would pay $74,204 in taxes over the nine-year abatement.

The city had been trying to redevelop the block for more than a decade. The Redevelopment Commission bought the Fat Daddy's building in early 2008, according to its June 6, 2008, minutes. In 2017, Commonwealth was the only bidder, offering the minimum price of $45,000, and the commission's agreement at the time included up to $1.7 million from the commission to save the buildings' historic east and north facades, according to Sept. 14, 2017, minutes. In 2019, staff told the commission that Commonwealth's bid "depended on state tax credits" and that "they did not receive the tax credits at that time." The commission approved a new $45,000 purchase agreement on June 13, 2019, again contingent on the credits.

The buildings came down first. In December 2018 the commission approved $540,000 for demolition after a low bid of $500,000, according to its Dec. 13, 2018, minutes. The commission still holds artifacts from the old facade, a 2023 agenda memo says.

The tax credits did not come. In a July 2022 letter to the council, the city's community investment staff recalled the abatement for Commonwealth "at the Fat Daddy's site" and wrote that the project was not "selected by the Indiana Housing and Community Development Authority for tax credits." Records reviewed for this story show no later activity on Commonwealth's plan. The 2020 designation was limited to three years.

The second try

In August 2022 the council approved an eight-year abatement for The Monreaux LLC at 505 S. Michigan St. Its petition named Devereaux Peters as managing member and Chateaux 14 Development LLC as the parent company. The site was city-owned and paid no property taxes, the department's report said.

The city's staff said the Indiana Housing and Community Development Authority announced a tax credit award for the project on Feb. 2, 2023.

Since then, the plan has gotten smaller and the city's share larger:

2020 Commonwealth plan 2022 Monreaux plan 2025 Monreaux plan
Apartments 60 (seniors) 60 57
Building size Not stated 65,000 sq. ft. 56,000 sq. ft.
Private investment $8.74 million $13.7 million (2023 agreement) $17.7 million
City forgivable loan None $2.3 million (2023) $3.3 million

The Redevelopment Commission agreed in November 2023 to provide up to $2.3 million in tax increment financing money — property taxes collected from growth in a district and spent within it — as a loan to the developer and Delta Ventures Ltd., a nonprofit the commission's memo describes as created under common ownership with The Monreaux LLC. In June 2025 the city proposed raising the loan to $3.3 million and the private investment requirement to $17.7 million, while cutting the minimum to 57 units. Of those, 24 are to be for households at or below 50% of area median income, 21 at or below 80%, and 12 at market rate, according to the department's June 3, 2025, letter. The loan is forgiven if the building is finished within 36 months of closing and private investment tops $17.7 million, the letter says.

A city presentation to the council on Oct. 13, 2025, listed "Redevelopment Commission Support" of $3,603,000 and a total project cost of at least $21,303,000. In January 2026 the Board of Public Works awarded Miller's Building Supply a $303,000 contract, paid from River West TIF money, to buy sheathing and trusses for the building.

Deadlines pushed back

The Monreaux has also needed more time. The commission amended the land sale agreement at least five times; the fifth amendment, in September 2025, extended the closing deadline to Nov. 30, 2025, and gave the commission the right to retake the land if the buyer did not close on all construction financing.

The tax break's own three-year window expired Aug. 8, 2025. In October 2025 the council was asked to extend it to Dec. 31, 2028; the proposed resolution states that "completion of the project by end of the original designation period was not possible." The city estimated the Monreaux would pay $304,592 in taxes during the eight-year abatement and have $433,494 abated.

A Public Works permit lets the developer use the Monroe and Michigan street right of way for construction from April 1, 2026, through Feb. 1, 2027. The records reviewed do not give a completion date.

What did you think of this story?

More stories about Indiana Housing and Community Development AuthorityMonreauxMonreaux LLCRiver West Development AreaSouth Bend Common CouncilSouth Bend Redevelopment Commission

Comments

No comments yet.

This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.