Great Lakes spec warehouse cost $14.5M, below tax-break estimate
The 296,000-square-foot Dylan Drive building was finished in December 2024, and the city rates its 2022 abatement substantially compliant. Records name no tenant.
Older records: Published November 27, 2026. The main records behind this story run through June 2025.
Updated November 27, 2026 at 1:53 AM: Correction: An earlier version said the city's 2022 abatement report rated the project in compliance. That report listed it as a new abatement not yet required to report; the 2023 report rated it in compliance. It also said Lori Hamann called for a better tool for the council; the minutes say for th
When a Great Lakes Capital company asked South Bend for a tax break in 2022 to build a speculative warehouse on Dylan Drive, it had no tenant, and council members said so. Two years later the 296,000-square-foot building was finished for less than the company estimated, city reports show, and the city rates the deal substantially in compliance.
The newest of those reports covers 2024 and was filed in June 2025. The South Bend Paper did not find a newer city report on the project.
What was promised
GLC Portage Prairie V LLC, which the city identified as a subsidiary of Great Lakes Capital, petitioned in May 2022 to build the warehouse on 30 acres in the Ameriplex industrial park near Dylan Drive and Adams Road, later addressed as 5910 Dylan Drive. It estimated the cost at $15,318,200 and projected 50 to 200 indirect full-time jobs.
The Department of Community Investment's report called the building speculative, with a few tenants showing solid interest. Its schedule had the abatement start at 100% and fall 5 points a year to 70% over seven years. It estimated $1.88 million in taxes abated and $688,535 paid during those seven years, and about $367,600 a year in taxes once the break ends. The land paid about $1,565 in 2022.
The report also said the petitioner had not been granted any tax abatements. That was true of the new LLC, but city records list four earlier abatements in the same park for other Great Lakes Capital companies, approved in 2015, 2017 and 2019.
The council debate
Council members pressed on the jobs figure. Lori Hamann said the council's Community Investment Committee needed a better tool for judging a spec building with no tenant, according to the May 23, 2022, minutes. Caleb Bauer, then acting executive director of community investment, said no tenant was lined up and the job estimate drew on Great Lakes' earlier buildings. Isaac Hall of Great Lakes Capital told the council the estimate assumed about one job per 2,000 square feet.
Jeff Smoke, a Great Lakes Capital managing director, said the company was in serious talks with a tenant for 250,000 square feet. Asked by Council Member Eli Wax whether the project could go ahead without the break, Smoke said the company would not move forward without one, the minutes show. He said taxes and operating costs are passed on to tenants in their rent.
Joseph Shabazz, who lives on Martin Luther King Drive, asked how contractors would be chosen and said the application was vague about minority participation. Bauer said the abatement requires an affirmative action plan.
The council designated the area with eight votes in favor on May 23 and confirmed the break with seven votes in favor on June 13, 2022, the minutes show. In September 2022 the Board of Zoning Appeals approved a variance allowing loading docks in a corner yard, over one letter of opposition, its minutes show.
What the records show since
The city's 2022 abatement report, filed in June 2023, listed the project as not started and as a new abatement not yet required to report, with a $15 million estimate, a Dec. 1, 2023, completion date and 50 new jobs. The 2023 report, filed with the council in September 2024, rated it a 1, in compliance.
The 2024 report tells a different story on cost and timing:
| Measure | 2022 petition | 2024 city report |
|---|---|---|
| Estimated cost | $15,318,200 | $16,418,200 |
| Actual cost | n/a | $14,527,610 |
| Expected completion | n/a | Jan. 1, 2024 |
| Actual completion | n/a | Dec. 1, 2024 |
| Compliance score | n/a | 2, substantially in compliance |
The actual cost is about $790,000 below the petition and about $1.9 million below the estimate the 2024 report lists. The records reviewed do not explain why the report's estimate is $1.1 million higher than the petition's.
The report's key says a score of 2 can mean a company missed a jobs goal on a relatively new project or did not reach its estimated project cost. It does not say which applied here. The paper did not find a count of jobs actually at the building in city records, or a record naming a tenant.
Under the 2024 report, the abatement first applies to 2025 tax bills and runs through 2031.
Great Lakes Capital has since won more breaks nearby. In August 2026 the council approved an eight-year abatement for GLC Mid-Bay LLC's spec warehouse on Chet Waggoner Court, and the city's report for that petition lists the Dylan Drive building among the company's prior abatements.
More stories about Caleb BauerGreat Lakes CapitalPortage PrairieSouth Bend Common Council
- Bill 22-21 packet: DCI letter, declaratory resolution, tax abatement report and schedule, petition, GLC Portage Prairie V LLC (May 18, 2022)(opens in a new tab)
- Resolution 4956-22, designating resolution, GLC Portage Prairie V LLC (May 23, 2022)(opens in a new tab)
- Resolution 4957-22, confirming seven-year real property tax abatement, GLC Portage Prairie V LLC (June 13, 2022)(opens in a new tab)
- Common Council Community Investment Committee minutes, May 23, 2022(opens in a new tab)
- South Bend Common Council minutes, May 23, 2022 (signed)(opens in a new tab)
- South Bend Common Council minutes, June 13, 2022 (signed)(opens in a new tab)
- Board of Zoning Appeals minutes, Sept. 6, 2022 (BZA#0132-22, 5910 Dylan)(opens in a new tab)
- City of South Bend 2022 Annual Tax Abatement Report (June 15, 2023)(opens in a new tab)
- DCI budget answers with 2023 Annual Tax Abatement Report (Sept. 12, 2024)(opens in a new tab)
- City of South Bend 2024 Annual Tax Abatement Report (filed June 13, 2025)(opens in a new tab)
- Bill 26-23: Declaratory resolution and DCI report, GLC Mid-Bay LLC, listing prior GLC abatements (Aug. 2026)(opens in a new tab)
This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.
Comments
No comments yet.
Comments use your real name. To keep out fake accounts, we verify a US mobile number by text. We never show or share your number. Comment guidelines
Commenting as .
Replying to a comment.
Be civil and stay on topic. Criticism of anyone, including this paper, is welcome. Comments are reviewed before they appear. Guidelines
Comments open soon.