Portage Prairie warehouses cost more than planned, city reports show

Great Lakes Capital's 315,000-square-foot 2017 building paid no property tax for six years under its abatement, and the council approved another GLC spec warehouse in August.

By South Bend Paper AI Desk · November 10, 2026 at 12:52 AM

Updated November 10, 2026 at 12:52 AM: Correction: An earlier version said the August approval was Great Lakes Capital's eighth abatement in the Portage Prairie area. City records list six earlier Portage Prairie abatements, making it the seventh; an eighth GLC abatement was for a property on North Sheridan Street.

When Great Lakes Capital asked for a tax break in 2017 to build a 315,000-square-foot warehouse at Adams Road and U.S. 31, the city's own report spelled out the deal: the building would pay no new property tax for six years, about $1.82 million abated in all, and then about $303,750 a year.

City records show the building went up, cost more than planned and was rated in compliance with its goals. That six-year break has now run its course, and in August the Common Council approved another abatement for a Great Lakes Capital spec building nearby, the company's seventh in the Portage Prairie area since 2015, city records show.

What was promised

GLC Portage Prairie III LLC, a Great Lakes Capital affiliate, told the city in February 2017 it would spend $13.5 million on a "spec commercial distribution and light assembly facility" and estimated the project would "create (100) one hundred permanent full-time jobs," according to the Department of Community Investment's report to the council. Staff qualified the project for nine years but recommended six, saying a shorter break "best meets the needs of both the developer and the City." The council confirmed it March 13, 2017.

The city's 2022 tax abatement report, filed in June 2023, lists the project's actual cost at $15.8 million against an estimate of $14.25 million, and its completion at Dec. 31, 2019, nearly two years after the expected date of Feb. 1, 2018. The report gives it a compliance score of 1, which its key defines as "in compliance with all goals, including project cost, jobs created and related salaries, and jobs retained and related salaries." The 2026 abatement filing lists the building's address as 5555 Dylan Drive.

The other phases

The same reports rate each finished Great Lakes Capital phase in Portage Prairie as in compliance. Three of four came in above their cost estimates:

Portage Prairie phases: estimated vs. actual costGreat Lakes Capital abatement projects; dollars, not adjusted for inflation
Estimated costActual cost
$0$5M$10M$15M$20MPortage Prairie (2015)$7M$7.9MPhase II (2017)$7.7M$7.4MPhase III (2017)$14.3M$15.8MPhase IV (2019)$7.2M$7.5M

Source: City of South Bend Department of Community Investment annual tax abatement reports, 2022 and 2023

Phase IV, a 166,000-square-foot speculative building approved in 2019 on the same corner, was not expected to create jobs directly. "Due to the speculative nature of the building, only indirect jobs will be retained or created," the city's report said. Its six-year break was estimated to phase in $962,891 in taxes.

Later abatements went to Phase V at 5910 Dylan Drive in 2022, a $15 million project, and to a $12 million AM General expansion at 5448 Dylan Drive in 2023, the city's records show.

The newest building

On Aug. 24, 2026, the council confirmed an eight-year abatement for GLC Mid-Bay LLC, another Great Lakes Capital company, to build a 132,620-square-foot speculative warehouse on Chet Waggoner Court. The department's presentation puts its cost at $8.8 million and says it "complements Portage Prairie's existing 1.35 million square feet of industrial space." It estimates 15 to 100 jobs "depending on future tenants," at about $25 an hour.

Unlike Phase III's full six-year break, the new schedule starts at 100% and falls to 40%. The city estimates the building will pay $1.32 million in taxes during the abatement and have $1.16 million abated.

Great Lakes Capital is also the developer of the Madison Lifestyle District downtown.

The paper's records search found no city filing that reports what taxes Phase III has paid since its break ended.

What did you think of this story?

More stories about Great Lakes CapitalPortage PrairieSouth Bend Common CouncilSouth Bend Department of Community Investment

Comments

No comments yet.

This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.