Board adds $155,000 to Kennedy Park rebuild for concrete courts

The Board of Public Works approved a change order bringing Garmong's contract to $15,991,908.83, swapping asphalt courts for post-tension concrete.

By South Bend Paper AI Desk · November 7, 2026 at 10:50 PM

Updated November 11, 2026 at 8:47 AM: Updated Nov. 11 with the Board of Public Works' approval of the change order and what the city's documents say it pays for.

The rebuild of Kennedy Park on South Bend's west side will cost just under $16 million after the Board of Public Works approved a second change order Tuesday that swaps the park's asphalt athletic courts for longer-lasting concrete.

Change Order No. 2 with Garmong Construction Services adds $154,981.88, bringing the contract to $15,991,908.83, according to a Nov. 10 letter from board clerk Hillary Horvath to the contractor.

What the money pays for

A Nov. 5 memo to the board from Patrick Sherman, the city's project manager, said the city was changing athletic courts "that were originally bid as asphalt to be post-tension concrete instead."

"The project was originally bid with asphalt athletic courts to ensure that we were able to have a project within budget," the memo said. After bidding, a review of the budget and discussions with Venues Parks & Arts and the Indiana Department of Natural Resources, "it was determined that the funding was available" for the change.

The memo said asphalt courts last about 10 years, compared with 25 to 40 years for post-tension concrete, and that the change would "reduce maintenance costs over time." The contractor's paperwork describes the work as a post-tension basketball court of about 5,000 square feet, similar to the park's pickleball court.

The memo also said the change order adds 14 days because of "unforeseen underground debris as well as utility delays outside of the contractor's control."

New completion dates

The signed change order lists three dates for substantial completion:

  • Trails, athletic courts and the new parking lot: Dec. 31, 2026
  • Pool: July 17, 2027
  • Whole project: Oct. 14, 2027

Earlier records gave July 2027 for the project. Change Order No. 1 set substantial completion for July 3, 2027, and Sherman told the Park Board in August the project was projected to be done in July 2027. At a Sept. 22 council budget hearing, Erin Thornton of Venues Parks & Arts said the groundbreaking took place in May and "a ribbon cutting for the new aquatic center and redesigned park is planned for the next summer," the minutes say.

What is being built

City officials have described the project as a complete rebuild of the park at Westmoor and Olive streets. In the August Park Board meeting, Sherman described "a complete rebuild with a new pool, athletic courts, and playground," according to the minutes. A 2024 Venues Parks & Arts presentation to the Common Council listed a new "inter-generational aquatics center, new parking lot, natural areas, picnic areas, new playground, and more."

The pool would be the only one the parks department operates, according to minutes of an August 2024 council budget hearing.

How the price got here

The board hired the contractor, named in the contract as C.H. Garmong & Son, as construction manager in October 2025. Under that arrangement, called construction manager as constructor, the firm helps plan the project, bids out the trade work and then guarantees a maximum price. The board approved the first contract, worth $10,000, on Oct. 28, 2025.

When Garmong applied for the job in August 2025, its proposal described "the City's established maximum budget of $13 million, inclusive of all construction and CMc services."

On April 14, 2026, the board approved a guaranteed maximum price of $15,802,659.

On May 12, the board added $34,267.95 in Change Order No. 1. A memo from Sherman said a bid package for building and pool general trades had first been set to go to Larson Danielson, based on a combined post-bid offer, but Public Works, city lawyers and Garmong decided it "must be awarded to the lowest package bidder, Gibson Lewis," whose $1,949,800 bid "was fully accurate to the scope and complied with all bidding requirements."

With both change orders, the contract is $189,249.83 above the April price, about 1.2%. Sherman's memo describes the latest change as 1% of the contract.

The 2024 Public Works annual report says the city won a $7.5 million National Park Service Outdoor Recreation Legacy Partnership grant, a matching grant for a $15 million project. The city's 2026 community investment budget presentation listed Kennedy Park among projects in a $34 million neighborhood improvement bond.

What did you think of this story?

More stories about Garmong Construction ServicesKennedy ParkSouth Bend Board of Public Works