Nimtz Parkway spec warehouse cost $2.9M less than tax-break plan

Holladay Properties' 2019 speculative building filled with a Polywood distribution center, and city reports rate it in compliance despite a missed tax form.

By South Bend Paper AI Desk · November 9, 2026 at 7:50 AM

Older records: Published November 9, 2026. The main records behind this story run through September 12, 2024.

A speculative warehouse that won a six-year South Bend property tax break in 2019 was built for about $10 million, roughly $2.9 million less than the $12.94 million its developer estimated, city reports show. The city still rates the project in compliance with all of its goals.

The 225,000-square-foot building at 24605 Cleveland Road, which later city reports list as 6701 Nimtz Parkway, was proposed by 31 Nimtz Land LLC, an affiliate of Holladay Properties. It was built without a tenant, a so-called spec building, at the northwest corner of U.S. 31 and Nimtz Parkway.

What was promised

The company's April 2019 petition said it would spend about $12.94 million to build the 40-dock distribution building on 19.6 acres in the River West tax increment financing (TIF) district. Because no tenant had signed, the petition listed jobs as "Unknown" and said, "We fully expect that new jobs will be created as a result of this new industrial building being constructed." The city's staff report said "only indirect jobs will be retained or created."

On its scoring sheet for public benefits, the petition also marked "yes" for supporting a city facility, naming the Potawatomi Zoo, an item worth 84 of its 226 claimed points. The records reviewed for this story do not show whether a donation was made.

The Common Council designated the site on April 8, 2019, and confirmed the abatement May 13, 2019, in Resolution 4785-19. It phases in property taxes on the new building over six years: no tax on the new value for three years, then 5% for three years.

City staff estimated the break would forgive about $1.79 million in taxes over the six years, with $149,218 paid in that time. Taxes on the land were under $6,500 a year before construction, the staff report said.

A missed form, then a waiver

Construction began in October 2019 and finished in November 2020, Paul Phair of Holladay Properties told a council committee in June 2021. A lease for the whole building was signed in July 2020 with Poly-Wood, which the city described as "a local manufacturer now utilizing it as their distribution center," on an 86-month lease.

The company did not file the county form needed to claim the deduction for taxes payable in 2021. It received a spring 2021 tax bill and paid $61,874.54, according to a June 9, 2021, letter from Daniel Buckenmeyer, the city's director of economic resources and business development.

In a May 2021 letter to the city, Phair wrote that "the error in compliance is due to our misunderstanding of reporting timeframes in the instance of a speculative building," and that the company had believed forms were not due until the building was complete and fully assessed. "We apologize for the misunderstanding," he wrote.

Buckenmeyer told the committee that, if the waiver passed, the extra amount would be credited on a later tax bill, and that after the abatement the city could expect about $300,000 in new tax revenue, the minutes say. Asked by Councilmember Troy Warner when Holladay seeks abatements, Phair said the company had built only two spec buildings, which carry high risk, and that abatements help get such buildings up as soon as possible, according to the council minutes.

The council approved the waiver June 14, 2021, by a voice vote of 8-0. The resolution states the company "has met all objectives in its deduction application."

What the reports show since

The city's 2022 abatement report lists the project's actual cost at $10,049,989, about 78% of the estimate, and a completion date of Nov. 5, 2020. It gives the project a compliance score of 1, which the city's key defines as "in compliance with all goals, including project cost, jobs created and related salaries, and jobs retained and related salaries." The tables list no jobs promised, and two or three retained jobs and one new job reported.

Nimtz Parkway warehouse: estimated vs. reported costNominal dollars, one-time construction cost
$0$5M$10M$15M$12.9M2019 estimate$10MReported actual

Source: 31 Nimtz Land petition (2019); City of South Bend 2022 Annual Tax Abatement Report

By the city's 2023 report, filed in June 2024, the abatement was listed under a different owner, 4018 South Bend LLC, with the same cost figures and the same compliance score. The city records reviewed do not show when or how the property changed hands. The two reports also differ on timing: the 2022 report lists the final year of the break as 2026, the 2023 report as 2027.