South Bend's payments to one builder jump to $43 million in 2025

Checkbook records show Larson-Danielson Construction's city pay rose from $2.6 million in 2024 as Four Winds Field, the Morris addition and City Hall work overlapped.

By South Bend Paper AI Desk · November 4, 2026 at 8:16 PM

Updated November 6, 2026 at 1:50 PM: Updated Nov. 6: the chart of yearly payments is redrawn with years running left to right; the figures are unchanged.

The City of South Bend paid Larson-Danielson Construction Co. about $43 million in 2025, city checkbook records show. That's up from $2.6 million in 2024 and more than the city paid the LaPorte builder in 2020 through 2024 combined.

Three city building projects hit full construction in the same year: the renovation and expansion of Four Winds Field, the Raclin Murphy Encore Center addition to the Morris Performing Arts Center, and work the checkbook labels "City Hall renovations."

The money isn't new to Larson-Danielson. In 2019 the city paid the company $17.2 million, almost all of it ($16.4 million) for work labeled Howard Park. Payments then fell to between $12,500 and $2.6 million a year until 2025.

City of South Bend payments to Larson-Danielson ConstructionPayments by year, 2019–2025; nominal dollars, not adjusted for inflation. Combines the two names the checkbook uses for the company.
$0$10M$20M$30M$40M$50M$17.2M2019$1.4M2020$13K2021$871K2022$318K2023$2.6M2024$43M2025

Source: City of South Bend checkbook via the South Bend Transparency Portal

The chart combines payments recorded under "Larson Danielson Constr" (2019 to April 2020) and "Larson Danielson Construction Co" (May 2020 on). Figures are net of corrections.

Four Winds Field: $41.2 million paid so far

Most of the money is for the ballpark. Checkbook payments to Larson-Danielson from the fund used for the Four Winds project total $41.2 million: $1.4 million in late 2024, $23.2 million in 2025 and $16.6 million in 2026 through Sept. 22.

The city hired Larson-Danielson as its "construction manager as constructor," or CMc. Under that method, a builder joins the project during design and later agrees to a guaranteed maximum price, a cap on what the city pays unless the board approves a change. The Board of Public Works approved the company's professional services agreement on Nov. 14, 2023.

The board approved the work in three phases. According to the minutes of the board's Jan. 14, 2025 meeting, Project Manager Patrick Sherman said phase one, "approximately eleven-million dollars," covered demolition and steel for the second deck so the stadium could open on schedule in April. Phase two, about $4 million, covered a new splash pad, a relocated kids' bounce house and a new playground. Phase three, approved that day for $28,236,556, completed the contract and included a new four-story events building in left field. The amendment sets the guaranteed maximum price at $43,489,593.

On Aug. 25, 2026, the board approved Change Order No. 1, which adds $1,566,567.78 and 295 days. The new contract total is $45,132,658.78, and the completion date is Jan. 15, 2027. A memo from Sherman says the change order adds the third-floor office build-out in the events building "which was cut from the original project," a traffic coating on the concourse to stop water from leaking into the basements, and three canopies, one of them now required by the health department. The memo says the money comes from "project budget savings and bond interest dollars and did not require any general or TIF funding," and that this "is expected to be the only change order on the project."

Where the ballpark money comes from, and what the city gives up for it, is the subject of a separate story: Records show property-tax backstop behind Four Winds Field bonds. The renovation is financed with $44.86 million in city bonds repaid from state sales and income taxes the city is allowed to keep under the Professional Sports and Convention Development Area program.

A $27 million entry, corrected a week later

One line in the checkbook stands out. On Sept. 2, 2025, the checkbook records a $27,013,911.52 Four Winds payment to Larson-Danielson. A week later, on Sept. 9, a $24,780,235.02 entry labeled "CORRECTION" comes off the same fund, for a net of about $2.2 million. The totals in this story include both entries. The records don't explain the original amount.

The Morris addition and City Hall

Checkbook payments for the Raclin Murphy Encore Center add up to $16,099,214.79. That matches to the cent the project completion affidavit the Board of Public Works approved on Aug. 25, 2026. The affidavit describes a 20,000-square-foot building on the north side of the Morris Performing Arts Center at 211 N. Michigan St., with circulation space, restrooms, service support and event space. Of that total, $12.1 million was paid in 2025.

Payments labeled "City Hall renovations" add up to $7.9 million: $7.7 million in 2025 and $214,000 in June 2026. The portal's documents don't include the City Hall contract, so this story doesn't report its value.

The checkbook runs through mid-October 2026. This year the city has paid Larson-Danielson $21.2 million so far.

What did you think of this story?

More stories about Four Winds FieldLarson-Danielson Construction

Comments

No comments yet.

This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.