Ward Bakery rehab nears its investment pledge, city reports show
The Bakery Group reported $3.34 million spent on the vacant Portage Avenue landmark against $3.75 million promised, and the city paid $305,000 for its facade work.
Older records: Published November 18, 2026. The main records behind this story run through June 13, 2025.
Updated November 18, 2026 at 12:54 AM: Clarification: An earlier version said the building's owners owed $410,036 in unpaid taxes. The city report gives that as the unpaid taxes on the building since 2012 and does not say who owed them.
The Ward Baking Company building at 906-910 Portage Ave. sat empty from 2012, when Ford Distribution left, until a local development group bought it with a plan to fill it with small businesses. Unpaid property taxes on it since 2012 totaled $410,036, a city staff report said in 2021. Six proposals to fix it up with tax credits had failed.
In 2021 the city backed a new try. The Common Council approved two tax breaks for The Bakery Group LLC, and the Redevelopment Commission agreed to spend up to $300,000 in tax increment financing on the building's exterior. Here is what the company promised and what city records show since.
What was promised
The Bakery Group, led by President Mike Keen, estimated the renovation of the 56,000-square-foot art deco building would cost $3.75 million. Its petition described retail, maker and studio space, a cafe, offices and small-business training. The city report estimated the project would create two permanent full-time jobs and, through an estimated 60 tenants, at least 60 indirect jobs.
The council approved a four-year real property tax abatement, which phases in taxes on the renovation at 100%, 90%, 80% and 70% off, plus a two-year break for reopening a vacant building. Both passed 8-0 on June 14, 2021. At that meeting, Keen said the group had first sought tax credits to make the building affordable housing, but could not get them.
The Redevelopment Commission's August 2021 development agreement required at least $3.75 million in private investment and completion within 36 months. In exchange, the city would pay up to $300,000 from the River West TIF district, the tax increment financing district that captures growth in property taxes there, for windows, doors, storefront and masonry repairs.
What records show
The city's facade work. City checkbook records show $305,455 in payments labeled "Ward Bakery Exterior" from April 2022 to May 2024, to C&S Masonry Restoration and Werntz Supply. A 2022 amendment had the company pay the city $15,393 so the masonry contractor could keep working along the Portage Avenue facade.
A later deadline. The company missed the original September 2024 completion date. In September 2024 the commission took up a second amendment extending it by 18 months, which city staff said was "due to difficulty in sourcing materials," according to the minutes. Joseph Molnar, the city's assistant director of growth and opportunity, said the group had added new windows, masonry repairs, an HVAC system, plumbing repairs, flooring, structural repairs, a new roof, skylights and site work, and "has submitted all necessary reporting documents."
Keen told the commission the project would cost $5.2 million to $5.4 million by completion, more than the $3.75 million estimate, because of the focus on the exterior. He said the first phase would have room for about 35 to 40 tenants, six retail spaces, 13 maker and studio spaces on the lower level, and 18 to 19 offices.
Investment and jobs. The city's most recent annual tax abatement report, filed June 13, 2025, lists $3,336,882 in reported project cost against the $3.75 million commitment, with an estimated completion date of Oct. 15, 2024. It shows the abatement beginning with taxes paid in 2026 and running through 2029. The report lists no jobs for the project. A year earlier the report had listed $2,304,689.
That June 2025 report is the newest city compliance record found for the project, so the figures are about 17 months old. City records do not show whether the extended deadline in early 2026 was met.
Since then
The building is in use. In September 2026 the Board of Zoning Appeals approved a variance for a trash enclosure at 908 Portage Ave. so the building can "better serve the businesses within," according to the city staff report. No one from the public spoke, the minutes say.
More stories about Bakery Group LLCRiver West Development AreaSouth Bend Common CouncilSouth Bend Redevelopment CommissionWard Bakery building
- Bill 21-25 packet: DCI letter and tax abatement report, The Bakery Group LLC (May 18, 2021)(opens in a new tab)
- Resolution 4908-21, designating real property tax abatement, The Bakery Group LLC(opens in a new tab)
- Resolution 4909-21, confirming real property tax abatement, The Bakery Group LLC (June 14, 2021)(opens in a new tab)
- Resolution 4911-21, confirming vacant building tax abatement, The Bakery Group LLC (June 14, 2021)(opens in a new tab)
- South Bend Common Council minutes, June 14, 2021(opens in a new tab)
- Development Agreement, Redevelopment Commission and The Bakery Group LLC (Aug. 12, 2021)(opens in a new tab)
- First Amendment to Development Agreement, The Bakery Group, agenda memo (June 6, 2022)(opens in a new tab)
- Second Amendment to Development Agreement and memo, The Bakery Group (signed, Sept. 12, 2024)(opens in a new tab)
- Redevelopment Commission minutes, Sept. 12, 2024(opens in a new tab)
- City of South Bend 2022 Annual Tax Abatement Report (June 15, 2023)(opens in a new tab)
- DCI budget answers with 2023 Annual Tax Abatement Report (Sept. 12, 2024)(opens in a new tab)
- City of South Bend 2024 Annual Tax Abatement Report (filed June 13, 2025)(opens in a new tab)
- Board of Zoning Appeals agenda packet and staff report, Sept. 8, 2026(opens in a new tab)
- Board of Zoning Appeals minutes, Sept. 8, 2026 (unsigned)(opens in a new tab)
- City of South Bend checkbook: Ward Bakery exterior payments, 2022-2024, via the South Bend Transparency Portal(opens in a new tab)
This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.
Comments
No comments yet.
Comments use your real name. To keep out fake accounts, we verify a US mobile number by text. We never show or share your number. Comment guidelines
Commenting as .
Replying to a comment.
Be civil and stay on topic. Criticism of anyone, including this paper, is welcome. Comments are reviewed before they appear. Guidelines
Comments open soon.