Marion Street footbridge design costs to reach $584,425

A second amendment with Lochmueller Group adds $56,625 for permitting, soil testing and right-of-way work, months after the city hired Milestone to build the bridge.

By South Bend Paper AI Desk · November 8, 2026 at 9:52 AM

South Bend's Board of Public Works votes Tuesday on adding $56,625 to Lochmueller Group's design contract for the Marion Street pedestrian bridge over the St. Joseph River, bringing the firm's contract to $584,425.

The amendment, the second to the 2023 agreement, covers "additional design engineering services for Marion Street pedestrian bridge including permitting, geotech, and right-of-way," according to the board's Nov. 10 agenda.

The added work comes after construction was already bid. In March the board awarded Milestone Contractors a $3,965,897 contract to build the bridge.

Where the bridge goes

The bridge would carry a path from Marion Street on the west side of the river to the East Bank Trail on the east side, according to a February budget request to the Redevelopment Commission from Leslie Biek, assistant city engineer. "The bridge will have two spans and one concrete cylindrical column, placed in the middle of the river," the request says, with steel truss railings and handrail lighting like the rebuilt Coal Line Trail bridge.

Two trail projects would tie it into the city's network: a trail along the south side of Marion Street to Michigan Street, and a connector along Madison Street to the trail on Hill Street.

The February request said bridge construction was expected to begin in late summer and finish in spring 2027. Records reviewed do not give an updated schedule.

How the design bill grew

The board hired Lochmueller in November 2023 for engineering work capped at $97,000. In June 2025 it approved a first amendment for design services. The board's letter and agenda put that amendment at $430,000, but the amendment's own summary lists $430,800, for an adjusted contract of $527,800. Tuesday's amendment would add $56,625.

Contract step Date Amount
Original agreement Nov. 2023 $97,000
Amendment No. 1 June 2025 $430,800
Amendment No. 2 (proposed) Nov. 2026 $56,625
Total $584,425

Construction and funding

Two companies bid on construction in February. Milestone bid $3,965,897 for the base work plus one alternate; Rieth-Riley Construction bid $4,823,370.50 for the same package, according to the city engineer's award memo. The memo said "sufficient funds have been appropriated from River East Residential TIF." Tax increment financing, or TIF, uses growth in property tax revenue within a district to pay for public projects there.

The February budget request estimated the bridge at about $4.35 million, the Marion Street trail at $580,000 and the Madison Street connector at $900,000, a total of $5.83 million. It said the bridge had earlier received $3 million in River West bond money, with $2.23 million left after design, and asked the Redevelopment Commission for $3.6 million more from the River East Residential TIF.

In September the board awarded Rieth-Riley a $313,852 contract for the Marion Street trail connecting the bridge to the Michigan and Marion streets roundabout.

What did you think of this story?

More stories about Lochmueller GroupMarion Street Pedestrian BridgeMilestone ContractorsSouth Bend Board of Public Works

Comments

No comments yet.