Riverfront West design pushes city's Lochmueller payments past $1M

Payments to the engineering firm rose to $1.08 million in 2025 from $424,000 the year before, with two-thirds tied to the new neighborhood planned south of Wayne Street.

By South Bend Paper AI Desk · November 15, 2026 at 1:48 AM

Updated November 15, 2026 at 1:49 AM: Correction: An earlier version called Charlie Brach the city engineer. The minutes identify him only as an engineer.

South Bend paid engineering firm Lochmueller Group $1.08 million in 2025, more than double the $423,850 it paid the year before and the most in any year since at least 2019, city checkbook records show.

Most of the increase came from one job: designing streets and utilities for Riverfront West, the new neighborhood the city plans on about 17 acres between Wayne Street, Monroe Street, Martin Luther King Jr. Boulevard and the St. Joseph River.

Where the 2025 money went

Payments labeled Riverfront West totaled $731,676 in 2025, or 67.5% of everything the city paid Lochmueller that year, according to the checkbook. The rest went to design work on the Marion Street pedestrian bridge ($225,094), phase three of the Coal Line Trail ($113,606), Seitz Park ($12,641) and a $396 traffic calming payment.

City payments to Lochmueller Group by yearNominal dollars; 2026 is partial, through Oct. 13
$0$250K$500K$750K$1M$1.3M$541K2019$377K2020$225K2021$173K2022$589K2023$424K2024$1.1M2025$359K2026*

Source: City of South Bend checkbook via the South Bend Transparency Portal

Through Oct. 13 this year, the city has paid Lochmueller another $359,428, including about $100,000 more labeled Riverfront West. That brings Riverfront West payments to about $831,660 since 2025.

How the contract grew

The Board of Public Works hired Lochmueller on Jan. 28, 2025, for $141,700 in survey work on the site. A month later, on Feb. 25, the board added $613,500 for engineering design, bringing the agreement to $755,200, the amendment shows.

Two more amendments followed. On April 8, 2025, the board added $48,185 for boundary survey and platting work. On May 13, 2025, it added $219,800 for full design of an extension of Western Avenue into Riverfront West and signal changes at Western and MLK, bringing the total to $1,023,185. At that meeting, Charlie Brach, identified in the minutes as an engineer, said the work was "for extending Western Ave. into Riverfront West to meet Fellows," according to the minutes.

A fourth amendment, approved Feb. 10, 2026, added grant writing and cost-benefit analysis for a federal BUILD grant application at no added cost. Contract documents list the River West Development Area TIF as the funding source. Tax increment financing, or TIF, uses the growth in property taxes inside a district to pay for projects there.

Payments labeled Riverfront West through Oct. 13 equal about 81% of the $1,023,185 contract total.

The design Lochmueller produced became the basis for the construction contract. On Sept. 18, 2025, the board awarded C&E Excavating $5,979,535 to build the neighborhood's streets and utilities from Lochmueller's plans.

The checkbook records payments as the city made them and does not tie each one to a specific contract amendment. This story counts only payments whose checkbook description names Riverfront West.

What did you think of this story?

More stories about Coal Line TrailLochmueller GroupMarion Street Pedestrian BridgeRiverfront WestSouth Bend Board of Public Works

Comments

No comments yet.

This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.