Switch from New Zealand restroom adds $109,700 at Walker Field

City records say a state inspection rule for factory-built buildings, plus buried concrete and a damaged water line, raised the contract by $156,252.20.

By South Bend Paper AI Desk · November 28, 2026 at 8:50 AM

The restroom building planned for Walker Field was supposed to come from New Zealand.

That detail sits in the minutes of the South Bend Board of Public Works, and it accounts for most of a $156,252.20 increase the board approved Nov. 10.

The restroom is a prefabricated unit. According to the minutes, the building permit review turned up a requirement that such a unit be inspected during the manufacturing phase, at the facility where it is made. With the planned unit arriving from New Zealand, the minutes say, "it was deemed unfeasible to have a City inspector present during manufacturing."

So the project pivoted to another manufacturer.

The South Bend Paper previewed this change order on Nov. 6, working from the Nov. 5 agenda, before the city's explanatory memo was in its archive. A change order is a formal revision to a signed construction contract, used when the work or the price changes after the job is awarded.

The memo is now in the record. Project Engineer Zak Tebell wrote it on Oct. 30.

What the memo says

The manufacturer change, the memo says, "is primarily driven by State of Indiana permitting requirements for prefabricated structures." Such units must be permitted through the Industrialized Building Systems Program, which involves the contractor, the manufacturer and the Indiana Department of Homeland Security.

"This permitting requirement was not identified during design and was brought to our attention during the building permit review process," the memo says.

The city first worked with the original manufacturer to see whether its unit could complete the permitting, according to the memo. It then determined that another manufacturer able to obtain the approval "would provide a more practical path forward for the project."

That change costs $109,700. The memo's table labels it a "Client directed change." For comparison, the "Restroom Kit" line in the contractor's July bid was $330,828. The records reviewed do not give the new unit's total cost.

The other two items are labeled "Unforeseen."

One was underfoot. The project includes removing several asphalt tennis courts in poor condition, and when removal began, the memo says, "it was discovered that the asphalt had been overlaid on top of a thick concrete slab." It adds: "Asphalt tennis courts are not normally overlaid on top of concrete." Removing the slab costs $9,337.20.

The other was the water. The plan was to connect to the existing water infrastructure serving the field house. Once construction began, the memo says, that source "was not in suitable condition." Its condition was not known before construction and "was assumed to be in good working order due to the presence of a working water fountain." An alternative source was found, and longer piping and a meter vault add $37,215.

The figures below come from the table in Tebell's memo.

What makes up the Walker Field restroom change orderChange Order No. 1, approved Nov. 10, 2026; nominal dollars
$0$25K$50K$75K$100K$125KRestroom manufacturer change$110KWater service change$37KConcrete removal$9.3K

Source: City of South Bend Board of Public Works records

Together the three items raise the contract with Majority Builders, Inc. by 22.75%. Minutes of the Nov. 5 agenda review session record Tebell explaining that the change order is over the 20% threshold for those three reasons. The board approved it Nov. 10 on a roll-call vote.

Majority Builders was the lowest of three bidders when the board awarded the work July 28 for $686,737. The city's review form and approval letter list the new contract sum as $843,009.20. The paper's arithmetic puts it at $842,989.20, which is $20 less, and the records do not explain the difference.

The board also approved a $5,000 amendment for the architect, Kil Architecture/Planning, for consultation "due to Owner moving forward with Urben Blu for the restroom builder in lieu of Exeloo." That brings the firm's agreement to $70,250.

The review form lists no time extension. The completion date is May 22, 2027.

Walker Field has waited a while. In written answers to council questions from a 2019 budget hearing, the city said it had upgraded 22 park restrooms the year before, and that Walker Field's was one of two left out "due to structural issues with the buildings." The facility, the city wrote then, was "in the planning and financing phases."

Seven years later, the records give it a date.

What did you think of this story?

More stories about Majority BuildersSouth Bend Board of Public WorksWalker Field

Comments

No comments yet.

This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.