Walker Field's 1930s shelter house gets new roof, masonry work

City records show rounds of quotes that drew no takers, a grant nearly lost and a rejected $395,000 price before the WPA-era building's repairs were finished Oct. 13.

By South Bend Paper AI Desk · November 10, 2026 at 8:52 AM

On Aug. 26, 2025, the South Bend Board of Public Works opened quotations for the Walker Field House Restoration. The record of what came in runs three words: "No Quotations Received."

A quotation is a contractor's written price for a job. For this job, on that day, no contractor offered one.

The building nobody priced is the Walker Field Shelter House, at Ewing Avenue and Walnut Street in Walker Field Park. It was built in 1938–39 as a Works Progress Administration structure and was listed on the National Register of Historic Places in 2010.

"While Works Progress Administration structures are not uncommon in the State of Indiana, this building is unique in its design with an arcaded area with wading pool," consultant Kurt West Garner wrote in an Aug. 19, 2020, letter to the city. The National Register listing, he wrote, made it "eligible to receive preservation funding."

That funding is what the city spent the next six years chasing, and at one point came close to losing.

The paper trail starts Jan. 28, 2020, when the Board of Public Works approved $5,850 for American Structurepoint to do structural engineering on the shelter house. That September, the board hired Garner's firm for a feasibility study and help with a state historic preservation grant application. City budget presentations that August listed the goal in shorthand: "HPC & VPA to jointly apply for a grant to address the Walker Field Park Shelter." Those are the city's historic preservation staff and its Venues, Parks & Arts department.

The grant came. The contractors were harder to find.

When the board awarded the first restoration contract in February 2023, to Acculevel Commercial Group for $74,040, board attorney Michael Schmidt said the project had been bid multiple times in the previous year, according to the minutes, and "this was the last attempt before losing grant funding."

The minutes from that September, when the board approved Acculevel's completed work at the same $74,040, fill in more. Schmidt said the city advertised for quotes two or three times and "even tried to go to the open market." He credited project engineer Rebecca Plantz, whose efforts "were what finally made the project awardable." Acculevel, typically a subcontractor, "stepped up as prime for this project."

The money carried a condition. In exchange for $60,000 in federal grant-in-aid through the state historic preservation office, the city signed a covenant, approved by the Park Board on April 17, 2023. The city agreed to maintain the building for 15 years and to make no visual or structural alterations without the state's written permission.

One quote, at $395,000

The second phase followed the same pattern. City Public Works reports say the city received a $93,750 state matching grant, toward a $150,000 project, for "Walker Field Shelter House Roof Rehabilitation and Masonry Improvements." In January 2025 the board rehired Garner's firm, billed hourly and capped at $5,000, to check the work against the Secretary of the Interior's standards, a grant requirement.

Then came the August 2025 opening with nothing to open.

The roof went out again in January 2026. Nine firms appear on the city's tabulation. One responded: Slatile Roofing and Sheet Metal of South Bend, at $88,812, about 50% above the engineer's estimate of $59,150. The board awarded it Feb. 10. The job was to remove the asphalt shingle roof and install a new one, with drip edging, flashing, paint and lap siding where noted.

The masonry quotes were opened May 26. Again there was one, from Berglund Construction, for $395,000. On June 9 the board rejected all quotes "due to quotes exceeding available budget for project."

The city restructured the job and tried again. The July 14 version asked for a base price for tuckpointing, which is repairing mortar joints, plus three optional add-ons called alternates. Berglund quoted $25,000 for the base, less than half the engineer's $64,350 estimate, and $200,000, $178,000 and $52,000 for the alternates.

The board awarded the base plus the third alternate for $77,000, subject to final approval by state preservation staff. An engineer told the board the timing was meant to meet a deadline at the end of the federal fiscal year. The records reviewed do not say what the alternates covered.

On Oct. 13, the board approved completion affidavits for both jobs: Slatile's reroofing at $88,812 and Berglund's masonry at $77,000.

What the Walker Field shelter house work costConstruction contracts, nominal dollars, by final or awarded amount
$0$20K$40K$60K$80K$100K2023 restoration (Acculevel)$74K2026 roof (Slatile)$89K2026 masonry (Berglund)$77K

Source: South Bend Board of Public Works minutes and contract records

Together the three construction contracts come to $239,852. Minutes of the Common Council's Personnel and Finance Committee from a Sept. 15 budget presentation sum it up in a line: historic preservation "used historic preservation funds for roof, masonry, and paint work at the Walker Field Shelter House."

What the building will be used for is less clear. A June Park Board agenda listed an "Adult Field Day" at the shelterhouse on June 20, but the records reviewed do not show a planned future use. Separately, the city awarded a $686,737 contract in July for a new restroom building at the park.

What the records do show is a deadline. The 2023 covenant binds the city to preserve the qualities that put the shelter house on the National Register until Jan. 1, 2038, a century after construction began.

What did you think of this story?

More stories about South Bend Board of Public WorksSouth Bend Historic Preservation CommissionSouth Bend Venues Parks & ArtsWalker Field

Sources
  1. Board of Public Works minutes, Oct. 13, 2026 (completion affidavits)(opens in a new tab)
  2. Project completion affidavit, Walker Field Reroofing, Slatile, Oct. 13, 2026(opens in a new tab)
  3. Project completion affidavit, Walker Field House masonry, Berglund, Oct. 13, 2026(opens in a new tab)
  4. Amendment No. 2, K.W. Garner PSA, Oct. 13, 2026(opens in a new tab)
  5. Quote opening and award, Walker Field House masonry, Berglund, July 14, 2026(opens in a new tab)
  6. Board of Public Works minutes, July 14, 2026(opens in a new tab)
  7. Board of Public Works minutes, June 9, 2026 (rejection of quotes)(opens in a new tab)
  8. Board of Public Works minutes, May 26, 2026 (masonry quote opening)(opens in a new tab)
  9. Award quotation, Walker Field House Restoration Phase II roofing, Slatile, Feb. 10, 2026(opens in a new tab)
  10. Board of Public Works minutes, Feb. 10, 2026(opens in a new tab)
  11. Board of Public Works minutes, Aug. 26, 2025 (no quotations received)(opens in a new tab)
  12. PSA, K.W. Garner Consulting & Design, Jan. 14, 2025(opens in a new tab)
  13. 2025 Public Works Annual Report (filed Oct. 30, 2026)(opens in a new tab)
  14. 2024 Public Works Annual Report(opens in a new tab)
  15. Board of Public Works minutes, Sept. 26, 2023(opens in a new tab)
  16. Board of Public Works minutes, Feb. 14, 2023(opens in a new tab)
  17. Walker Field Shelter House covenant, 2023(opens in a new tab)
  18. Park Board minutes, April 17, 2023(opens in a new tab)
  19. PSA and proposal, K.W. Garner Consulting & Design, 2020(opens in a new tab)
  20. 2021 budget presentation, Departmental Goals & Accomplishments, Aug. 19, 2020(opens in a new tab)
  21. Board of Public Works minutes, Jan. 28, 2020(opens in a new tab)
  22. Personnel & Finance Committee minutes, Sept. 15, 2026(opens in a new tab)
  23. Park Board agenda, June 15, 2026(opens in a new tab)
  24. Award bid, Walker Field Restroom Building, Majority Builders, July 28, 2026(opens in a new tab)

Comments

No comments yet.

This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.