Walker Field restroom contract to grow 22.75% in one change order
A fourth change order on Riverfront West site work, also on the Nov. 5 agenda, would put that contract 23.5% over its award.
Two South Bend construction contracts are set to grow by more than a fifth of their original price, according to the agenda the Board of Public Works reviewed Nov. 5.
Majority Builders' contract for a new restroom building at Walker Field would rise by $156,252.20, a 22.75% increase in a single change order. C&E Excavating's contract for streets and utilities in the Riverfront West Urban Neighborhood would rise by $457,126.45, its fourth change order, bringing the total change to 23.51% and the contract to $7,385,330.45.
A change order is a signed amendment that adds, removes or alters work after a public contract is awarded. Indiana law says change orders that increase a project's scope "may not exceed twenty percent (20%) of the amount of the original contract," but a change order "issued as a result of circumstances that could not have been reasonably foreseen" does not count toward that limit. Every change order must be "directly related to the original public work project."
The agenda lists the amounts and percentages only. The city's archive does not yet hold the memos explaining either new change order, so the records reviewed do not show how much of either increase the city counts as added scope and how much as unforeseen conditions.
Walker Field
The board awarded the restroom project to Majority Builders on July 28 for $686,737, the low bid. An engineering memo described the work as a new restroom building, removal of existing tennis courts and utility connections, plus a parking lot seal and stripe (Alternate 1). The board did not award Alternate 2, repairs to the space inside the field house arcade, for which Majority bid $110,369.
The agenda puts the change order at $156,252.20 and the revised contract at $843,009.20. Those two figures are $20 apart: the original contract plus the increase comes to $842,989.20. The 22.75% figure matches the $156,252.20 increase.
The agenda also lists a $5,000 amendment to Kil Architecture/Planning's design contract for "additional permitting services" on the restroom building.
Riverfront West
The board awarded C&E Excavating the first phase of public infrastructure for Riverfront West in September 2025 for $5,979,535. It is paid from the Riverfront West tax increment financing (TIF) district, which spends property tax growth within its boundaries, and from the city's water and wastewater capital funds.
The earlier change orders came with explanations:
- April 14, 2026, $522,000 (8.73%): $34,000 for added water main and sanitary sewer work, $158,000 for "plan revisions to work around utility conflicts," and $330,000 "related to utility relocation delays." It also moved two milestone dates to Feb. 1, 2027, because of utility relocation delays, and the final completion date to Nov. 30, 2027.
- April 28, 2026, no cost: later dates for two more milestones.
- June 23, 2026, $426,669 (7.14%): $8,500 for added tree removal, $109,585 in "unforeseen conditions" including conduit for NIPSCO and removal of AT&T lines, $135,900 for "contract omissions" for fiber and gas conduit removal, and $172,684 for "owner requested changes" to conduit and handhole specifications for Choice Light. The board's approval letter gives the amount as $426,699; the change order form and the itemized costs give $426,669.
The June memo from Assistant City Engineer Charlotte Brach said the total change then stood at 15.87%, "of which 10.56% is attributable to unforeseen conditions." That 10.56% matches the whole first change order plus the $109,585 in unforeseen conditions from the third, though the memo does not itemize it.
Source: South Bend Board of Public Works records via the Transparency Portal
The second change order, which changed only dates, is left out of the chart. The fourth would add 7.64% of the original contract.
What comes next
The agenda review session lists items for the board's next regular meeting; the change orders take effect only if the board approves them. The records reviewed do not show the justification for either new increase or how the city has applied the state limit to them.
More stories about C&E ExcavatingMajority BuildersRiverfront WestWalker Field
- Board of Public Works Agenda Review Session, Nov. 5, 2026 (revised)(opens in a new tab)
- Indiana Code 36-1-12-18, change orders (2025 Indiana Code, via Justia)(opens in a new tab)
- Award Bid, Walker Field Restroom Building, Project No. 125-024, Majority Builders (July 28, 2026)(opens in a new tab)
- Board of Public Works minutes, Sept. 9, 2025 (Riverfront West award)(opens in a new tab)
- Award Bid & Approve Contract, Riverfront West Urban Neighborhood, Project No. 121-067, C&E Excavating (Sept. 2025)(opens in a new tab)
- Change Order No. 1, Riverfront West, Project No. 121-067 (April 14, 2026)(opens in a new tab)
- Change Order No. 2, Riverfront West, Project No. 121-067 (April 28, 2026)(opens in a new tab)
- Change Order No. 3, Riverfront West, Project No. 121-067 (June 23, 2026)(opens in a new tab)
This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.
Comments
No comments yet.
Comments use your real name. To keep out fake accounts, we verify a US mobile number by text. We never show or share your number. Comment guidelines
Commenting as .
Replying to a comment.
Be civil and stay on topic. Criticism of anyone, including this paper, is welcome. Comments are reviewed before they appear. Guidelines
Comments open soon.