City seeks $3 million in TIF to build Howard Park bandshell
A Nov. 12 Redevelopment Commission request puts construction at $6.25 million, up from a $4.4 million budget in the architect's summer proposal.
South Bend city staff asked the Redevelopment Commission on Nov. 12 for $6 million in tax increment financing to build the Howard Park bandshell, closing the funding gap that remained after design. Half of that money is to be paid back by a state grant, so the city's own share comes to $3 million.
TIF, or tax increment financing, sets aside property tax growth inside a district for projects in that district. The money would come from the River East TIF, according to the request from project engineer Lidya Abreha. When the state's $3 million READI 2.0 Arts & Culture grant is paid, that half is to be returned to the River East Residential TIF, the request says.
The city posted signed copies of the request with the meeting's other items after the Nov. 12 meeting. The commission's minutes, which would record the vote, have not yet been posted. Staff recommended approval.
A bigger construction number
The request puts the total estimated construction cost at $6.25 million:
Source: South Bend Redevelopment Commission budget request, Nov. 12, 2026
That is well above earlier figures. In a proposal included in its July and September contract amendments, the architect, HGA, listed a construction budget of $4,410,076. At the commission's July 23 meeting, Abreha put the whole project, design included, at about $6 million, and commissioners discussed about $2.5 million still needed for construction, according to the minutes. The commission had approved $550,000 for design earlier this year, The South Bend Paper reported.
The new request does not explain the increase. It says the design is 70% complete, a construction manager has been brought on and an early bid package has gone out for the glued laminated timber, or glulam, part of the bandshell. The Board of Public Works hired Shiel Sexton Company as construction manager in October, and poor soil at the site prompted extra borings that month to study foundation options, records show.
The request describes the goal as a covered outdoor stage for mid-sized ensembles, regional touring acts and festivals that would make Howard Park a four-season destination and send park visitors on to downtown restaurants and shops.
Also on the agenda
Two smaller requests went to the commission the same day, both with staff recommending approval:
- West Side Greenway: $85,000 from the West Washington TIF district for a planning charrette, conceptual design and a master plan to extend the Westside Greenway south through the Near West Side. Joseph Molnar, deputy director of community investment, wrote that leaders of the Near Westside Neighborhood Association asked to advance the plan. The district expired in 2025, with its last tax revenue arriving in 2026.
- Child care: $150,000 from the commission's general fund, also called the Pokagon-South Bend Fund, for Ready to Grow St. Joe's South Bend Strong Start initiative, on top of the city's existing $100,000 a year for the coalition's Quality Improvement Grants. The memo from Darryl Scott, executive director of community investment, says 43 South Bend child-care programs received $200,846 in those grants in 2025, and that Strong Start received scholarship applications for 89 children on the first day they opened. It asks that the agreement set measurable South Bend outcomes and reporting rules.
The commission's next meeting is Monday, Nov. 23, moved because of Thanksgiving.
More stories about HGAHoward ParkHoward Park BandshellNear Westside Neighborhood AssociationReady to Grow St. JoeSouth Bend Redevelopment CommissionWest Side Greenway
- Redevelopment Commission budget request, Howard Park Bandshell construction (Nov. 12, 2026, signed)(opens in a new tab)
- Redevelopment Commission agenda, Nov. 12, 2026(opens in a new tab)
- Redevelopment Commission budget request, West Side Greenway Extension Planning (Nov. 12, 2026, signed)(opens in a new tab)
- Redevelopment Commission budget request, Ready to Grow St. Joe / South Bend Strong Start (Nov. 12, 2026, signed)(opens in a new tab)
- Amendment No. 3 to PSA, Howard Park Final Design, HGA (Board of Public Works, Sept. 22, 2026)(opens in a new tab)
- Amendment No. 1 to PSA, Howard Park Bandshell, HGA (July 14, 2026)(opens in a new tab)
- Redevelopment Commission packet Aug. 13, 2026 (July 23 minutes)(opens in a new tab)
- Contract, CMc Howard Park Bandshell, Shiel Sexton Company (Oct. 13, 2026)(opens in a new tab)
- Amendment No. 1 to PSA, Howard Park Bandshell, Abonmarche (Oct. 27, 2026)(opens in a new tab)
- South Bend Paper: Howard Park bandshell plan adds fencing for major events(opens in a new tab)
This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.
Comments
No comments yet.
Comments use your real name. To keep out fake accounts, we verify a US mobile number by text. We never show or share your number. Comment guidelines
Commenting as .
Replying to a comment.
Be civil and stay on topic. Criticism of anyone, including this paper, is welcome. Comments are reviewed before they appear. Guidelines
Comments open soon.