Sunday, November 29, 2026Sun, Nov 29

The South Bend Paper

Development, money and daily life in Michiana

Community

Howard Park bandshell plan adds fencing for major events

The $6 million riverside venue has a $3 million state grant, poor soil under its site and about $2.5 million in construction costs still unfunded.

By South Bend Paper AI Desk · November 7, 2026 at 9:05 PM

The design papers for South Bend's planned Howard Park bandshell call for more than a stage. They call for a fence.

An Aug. 28 add-service proposal from the project's architect, HGA, says the design team discussed "a gateway element by the Experience Lodge on South Saint Louis Boulevard, with a combination of permanent and mobile fencing throughout Howard Park to enclose the park during major events." The Board of Public Works approved the amendment Sept. 22, records show. It pays HGA $12,000 to design the fencing and $30,000 to design the roof structure.

The bandshell is planned for the event lawn at Howard Park, 219 S. St. Louis Blvd., along the St. Joseph River. A July 17 memo to the Redevelopment Commission describes it as "a state-of-the-art covered, open-air performance venue intended to attract regional visitors through diverse music, entertainment, and theatrical programming."

HGA's proposal, included in a Sept. 22 contract amendment, says "The City desires an iconic bandshell form whose design and materials reflect the history of South Bend and the beautiful park and river area and relate to existing park buildings." As for seating, "Audience seating will utilize the existing gently sloping lawn." The plans also call for enclosed support spaces, including a green room, an AV/IT room and storage, plus theatrical lighting and sound systems.

The roof will be glulam, or glued laminated timber. HGA's August proposal says a glulam pricing set "will lock in the approximate shape and form of the bandshell" and where "the three (3) glulam support points will be located." The fabricator will be engineer of record for that structure; HGA designs the foundations and the concrete stage and walls.

Those foundations need more study, records show. Abonmarche Consultants of South Bend was hired Sept. 22 for $26,500 to survey the site and drill seven borings. On Oct. 27 the board approved $7,800 more for two 50-foot borings "due to poor near-surface soil conditions identified during the September 11 borings and subsequent structural loading information provided by HGA," to "further evaluate foundation solutions," according to the amendment.

Who pays, and what is left

At the Redevelopment Commission's July 23 meeting, Commissioner Gooden-Rodgers asked the total cost. Project engineer Lidya Abreha said $6 million including design, according to the minutes. HGA's June-revised proposal puts the construction budget at $4,410,076 and the total project budget at $5,433,590.

The city has lined up a $3 million READI grant from the Indiana Economic Development Corporation and $250,000 from the Tourism Capital Investment Fund, records show. Locally, the commission approved $250,000 for preliminary design in March and $300,000 more on July 23 from the River East Residential TIF. TIF, or tax increment financing, sets aside property tax growth inside a district for projects in that district.

President Relos asked whether that would finish design, with about $2.5 million still needed for construction. Joseph Molnar, deputy director of community investment, said yes, and that the outside money already secured covers more than half the total project cost, according to the minutes.

HGA's design contract has grown in four steps, from $31,934 for preliminary design to a total of $574,506, records show. On Oct. 13 the board approved a $20,000 pre-construction contract with Shiel Sexton Company of Indianapolis, chosen as construction manager as constructor: a builder hired during design who later commits to a guaranteed maximum price. Five firms had submitted proposals Aug. 11. Board member Murray Miller voted no; the minutes give no reason.

The case for it, and a concern

Why build it? Vice President White asked July 23 how many outdoor venues the city has. Molnar said Potawatomi Park has an amphitheater and Seitz Park's stage is small, and that a Howard Park stage would allow larger events and simultaneous festival performances, with truck access and electrical service already installed in the 2019 redevelopment, the minutes say.

The project has drawn at least one objection on the record. At the Park Board's May 18 meeting, Mark Settnem "raised concerns about the potential noise issues and environmental impacts of the proposed Howard Park Bandshell, as well as the city's track record with outdoor pools," the minutes say. They do not give where he lives, and they record no response from the board or parks staff.

Plans target construction in 2027. Records posted so far do not show a guaranteed maximum price, a source for the remaining roughly $2.5 million, an operator, ticketing plans or capacity.

What did you think of this story?

More stories about Abonmarche ConsultantsHGAHoward ParkHoward Park Bandshell

Comments

No comments yet.

This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.