Poor soil prompts deeper borings at Howard Park bandshell site
The Board of Public Works approved $7,800 on Oct. 27 for two 50-foot borings, and design documents target construction from March to November 2027.

Engineers planning a new bandshell at Howard Park will drill deeper after soil tests this fall turned up weak ground near the surface, according to city records.
At its Oct. 27 meeting, South Bend's Board of Public Works approved a $7,800 amendment to the city's survey and soil-testing contract with Abonmarche Consultants. The amendment says the work is needed "due to poor near-surface soil conditions identified during the September 11 borings and subsequent structural loading information provided by HGA," the project's architect.
The added work covers two 50-foot borings at the site, laboratory testing, utility clearance and staking. The amendment says the goal is "to further evaluate foundation solutions" for the bandshell. It raises Abonmarche's contract from $26,500 to $34,300.
The records do not say what foundation the bandshell will need or whether the soil findings will change its cost or schedule.
What the city is building
The bandshell is planned for the lawn at Howard Park, 219 S. St. Louis Blvd., along the St. Joseph River. A design proposal from Hammel, Green and Abrahamson Inc. (HGA), a Milwaukee firm, describes an open-air stage for music, entertainment and theater, with a green room, audio-visual room and storage. Audiences would sit on the park's existing sloping lawn.
The proposal says the city wants "an iconic bandshell form whose design and materials reflect the history of South Bend and the beautiful park and river area." Its structure is to be glued-laminated timber, known as glulam, with the supplier designing the timber frame and HGA designing the foundations.
HGA's proposal, last revised June 12, puts the construction budget at $4,410,076 and the total project budget at $5,433,590, including design fees, consultants and contingencies.
Design contracts this year
The Board of Public Works has approved several design contracts for the project in 2026:
- July 14: $113,608 to HGA for design work.
- Sept. 22: $42,000 to HGA for glulam and fencing design, and $386,964 to HGA to take the design from 40% to final.
- Sept. 22: $26,500 to Abonmarche for a topographic survey and soil testing.
- Oct. 13: $20,000 to Shiel Sexton Company for preconstruction services. Shiel Sexton was the construction manager chosen from proposals the city opened in August.
- Oct. 27: the $7,800 soil-boring amendment.
At the Sept. 22 meeting, board member Abigail Magas asked why the two HGA amendments were listed separately. According to the minutes, city engineer Lidya Abreha explained that one was a scope adjustment and the other advanced the design to 100%, and that they "could have been condensed into one amendment."
How it is paid for
Board records list the River East TIF as the funding source. Tax increment financing, or TIF, sets aside growth in property tax revenue within a district for projects there.
A July 17 request to the Redevelopment Commission sought $300,000 from the River East Residential TIF to finish design. It said the commission approved $250,000 for design in March and that the city had since secured $3 million in READI grant money from the state and $250,000 through the TCIF grant program.
Timeline
HGA's revised schedule targets putting the project out to bid around Dec. 1, with a pre-bid site walk Dec. 16. Construction is targeted for March through November 2027, with close-out by December 2027.
Public comment
Not everyone has welcomed the plan. At the Park Board's May 18 meeting, Mark Settnem "raised concerns about the potential noise issues and environmental impacts of the proposed Howard Park Bandshell, as well as the city's track record with outdoor pools, recommending consultation with local country clubs for pool maintenance expertise," according to the amended minutes. The minutes do not give his street or neighborhood, and they do not record a response from the board to his comments.
More stories about Abonmarche ConsultantsHGAHoward ParkHoward Park BandshellSouth Bend Board of Public Works
- Amendment No. 1 to PSA – Howard Park Bandshell, Project No. 125-052 – Abonmarche Consultants (Board of Public Works, Oct. 27, 2026)(opens in a new tab)
- Amendment No. 3 to PSA – Howard Park Bandshell Final Design – HGA (Sept. 22, 2026), includes HGA proposal revised June 12, 2026(opens in a new tab)
- Amendment No. 2 to PSA – Howard Park Bandshell Glulam and Fencing – HGA (Sept. 22, 2026)(opens in a new tab)
- Amendment No. 1 to PSA – Howard Park Bandshell – HGA (July 14, 2026)(opens in a new tab)
- PSA – Howard Park Bandshell Survey and Geotech – Abonmarche (Sept. 22, 2026)(opens in a new tab)
- Contract – CMc Howard Park Bandshell – Shiel Sexton Company (Oct. 13, 2026)(opens in a new tab)
- Board of Public Works minutes, Sept. 22, 2026(opens in a new tab)
- Redevelopment Commission budget request – Howard Park Bandshell design (July 17, 2026)(opens in a new tab)
- Park Board minutes, May 18, 2026 (amended)(opens in a new tab)
- Park Board minutes, May 18, 2026 (original)(opens in a new tab)
This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.
Comments
No comments yet.
Comments use your real name. To keep out fake accounts, we verify a US mobile number by text. We never show or share your number. Comment guidelines
Commenting as .
Replying to a comment.
Be civil and stay on topic. Criticism of anyone, including this paper, is welcome. Comments are reviewed before they appear. Guidelines
Comments open soon.